Home Decisions

Decision 109/2024

Decision Notice 109/2024: Lochaber Smelter: interactions with Greensill Capital (UK) Limited

Authority: Scottish Ministers
Case Ref: 202200181


Summary

The Applicant asked the Authority for a copy of all interactions with Greensill Capital (UK) Limited in connection

with the Lochaber Smelter Guarantee and Reimbursement Agreement (GRA).  The Authority disclosed some information,

and withheld the remainder under a number of exemptions in FOISA.  The Commissioner investigated and found that

the Authority had generally complied with FOISA in responding to the request.


Relevant statutory provisions

Freedom of Information (Scotland) Act 2002 (FOISA) sections 1(1), (2), (4) and (6) (General entitlement); 2(1)(b)

(Effect of exemptions); 30(c) (Prejudice to effective conduct of public affairs); 47(1) and (2) (Application for

decision by Commissioner)

The full text of each of the statutory provisions cited above is reproduced in Appendix 1 to this decision. The

Appendix forms part of this decision.


Background

1.    On 23 May 2021, the Applicant made a request for information to the Authority.  The Applicant asked for a

copy of all interactions (to include, but not be limited to, all letters, emails, minutes and notes of meetings)

with Greensill Capital (UK) Limited in connection with the Lochaber Smelter GRA.

2.    The Authority responded on 22 June 2021, informing the Applicant, in terms of section 17(1) of FOISA, that

it did not hold the information requested.

3.    On the same day, the Applicant wrote to the Authority requesting a review of its decision.  The Applicant

stated that they were dissatisfied with the decision because they considered the Authority did hold the

information requested.

4.    The Authority notified the Applicant of the outcome of its review on 20 July 2021, upholding its original

decision without modification.

5.    On 3 August 2021, the Applicant wrote to the Commissioner, applying for a decision in terms of section

47(1) of FOISA.  This resulted in the Commissioner issuing Decision 046/2022 , requiring the Authority to issue a

revised review outcome, otherwise than in terms of section 17(1) of FOISA.

6.    On 9 February 2022, the Authority issued its revised review response to the Applicant.  The Authority

disclosed information in redacted form, withholding the redacted information under the exemptions in sections

33(1)(b) and 38(1)(b) of FOISA.

7.    On 9 February 2022, the Applicant wrote to the Commissioner, applying for a decision in terms of section

47(1) of FOISA.  The Applicant stated that they were dissatisfied with the outcome of the Authority’s review for

the following reasons:

  • they considered the Authority held more information than it had provided
  • the FOISA exemptions claimed do not apply to the withheld information
  • the public interest test was not carried out properly, as it favours disclosure of the withheld information
  • they considered there had been a deliberate attempt to conceal the information requested because of the

     high-profile issues that have been impacting Greensill.  

Investigation

8.    The Commissioner determined that the application complied with section 47(2) of FOISA and that he had the

power to carry out an investigation.

9.    The Authority was notified in writing that the Applicant had made a valid application.  The Authority was

asked to send the Commissioner the information withheld from the Applicant.  The Authority provided the

information and the case was subsequently allocated to an investigating officer.

10.    Section 49(3)(a) of FOISA requires the Commissioner to give public authorities an opportunity to provide

comments on an application.  The Authority was invited to comment on this application and to answer specific

questions.  These related to the Authority’s justification for withholding the information requested under the

exemptions in sections 33(1)(b) and 38(1)(b) of FOISA.

11.    During the investigation, the Authority informed the Commissioner that it wished to withdraw its reliance

on the exemption in section 33(1)(b) of FOISA, and instead wished to rely on section 30(c) to withhold the

information (for which it provided supporting submissions).

12.    On 21 December 2022, the Authority notified the Applicant of its change of position and disclosed to them

the name of a senior official it had previously withheld.

13.    On 16 February 2023, the Authority provided an updated response to the Applicant.  The Authority provided

a weblink to information that it had originally not marked for disclosure, but which it subsequently identified

had been published in relation to a previous information request .  The Authority also disclosed further

information from an email dated 31 January 2020, which it had previously withheld.

14.    The Authority also provided to the Commissioner an updated copy of an email dated 9 March 2020, as it had

located a later version with additional information. During the investigation, the Authority disclosed that email

to the Applicant, but withheld some of the additional information under the exemption in section 30(c) of FOISA.

15.    During the investigation, the Applicant provided comments on why they considered the public interest test

favoured disclosure of the information that was now being withheld under the exemption in section 30(c) of FOISA.

16.    The Applicant also confirmed that they did not require the Commissioner to reach a finding on the

Authority’s application of the exemption in section 38(1)(b) of FOISA in relation to junior officials.

17.    The Commissioner is satisfied that only personal data of junior officials have been withheld under the

exemption in section 38(1)(b) of FOISA.  Consequently, his investigation has not considered this matter further.

Commissioner’s analysis and findings

18.    The Commissioner has considered all of the submissions made to him by the Applicant and the Authority.  

Background: Lochaber Smelter Guarantee

19.    The Authority provided detailed background information, the following parts of which may be helpful in

explaining the background of the Lochaber Smelter Guarantee:

20.    The Lochaber aluminium complex in Fort William is the UK’s last remaining aluminium smelter, the operation

of which is a key component of Scotland’s industrial capability and a major source of employment in the West

Highlands.

21.    When Rio Tinto decided to review its Lochaber operations in 2016, the smelter faced the prospect of

closure, endangering over 300 jobs in total (direct, indirect and induced).  The Authority’s focus at the time was

to avoid the fragmentation of the Lochaber complex, to secure the long-term viability of the smelter and to

realise further industrial and employment opportunities on site.

22.    In September 2016, as part of the Authority’s wider overall objective to preserve jobs, protect the

economy and sustain the metals industry in Scotland, it indicated a willingness to support any purchaser who would

retain the smelter and associated hydro-power scheme together, and make the necessary commitment to significant

investment in the development of the Lochaber assets.  The Authority’s offer included the potential to guarantee

the power purchase obligations of the aluminium smelter and was made known on an even-handed basis to all short-

listed bidders via the vendor (Rio Tinto).

23.    To deliver its objective for the site, the Authority is standing behind a portion of the power purchase

obligations of the aluminium smelter operator (Alvance British Aluminium Limited (SmelterCo)) in the event that it

cannot pay for the power it is contracted to take from the hydro-electric power station operator (Simec Lochaber

Hydropower 2 Limited (HydroCo)).  Both companies are part of the GFG Alliance (GFG) which is a collection of

global businesses and investments.

24.    The commercial guarantee arrangement (the Guarantee) was entered into in December 2016 by the Authority,

SmelterCo and HydroCo, and guarantees over a 25 year term that the Authority will pay for a percentage of the

power that SmelterCo is contracted to purchase from HydroCo in the event that SmelterCo is unable to do so.

25.    The nominal value of the Authority’s contingent liability on day one of the Guarantee was £586 million

(i.e. the total amount of payments guaranteed by the Authority across the 25 year agreement), and is the largest

industrial guarantee ever agreed by the Authority.

26.    In return for the Guarantee, the Authority receives a commercial guarantee fee (the Fee) from GFG.

27.    In March 2021, GFG’s major providers of working capital and investment finance (Greensill Capital (UK)

Limited and Greensill Capital Management Company (UK) Limited (together “Greensill”)) entered administration.

28.    The Authority submitted that should the Lochaber Guarantee be called in and if other recovery options

prove ineffective, it would have an option to take ownership of the business assets at Lochaber and trade these

assets (directly or through lease arrangements) with the intent of satisfying the ongoing payment obligations

under the Power Purchase Agreement (PPA) or alternatively seek to dispose of the assets through a managed sales

process.  

29.    The Authority submitted that information within the material remained current and could negatively impact

its ability to operate the assets on effective commercial terms and, potentially, inhibit any sale process to the

detriment of the public purse if the information was disclosed prematurely.

The Applicant’s perspective

30.    Following the issue of Decision 062/23  and Decision 063/23  on 20 June 2023 (which also related to the

Lochaber Smelter GRA), the Applicant wrote to the Commissioner (on 21 June 2023 and on 31 July 2023) to advise him

that they strongly disagreed with the outcome.  

31.    The Applicant explained that the Commissioner appeared to have accepted information provided to him by the

Authority at face value and without adequate challenge.  In their view, the Guarantee did nothing for the

preservation of jobs at the smelter, but guaranteed the income for the hydro-plant only, which had very few direct

jobs.  In their view, “the story of saving jobs is concocted to divert attention away from the real purpose (a

financial enabler to allow the GFG Alliance to purchase the company)”.

32.    The Applicant also wrote to the Commissioner on 26 June 2023, contesting in more detail the accuracy of

the background information provided by the Authority in paragraphs 16 and 13 of those Decisions respectively.  The

Applicant provided what they described as an “alternative background”, as set out below:

  • The primary purpose of the Guarantee was to enable GFG to purchase Alcan Aluminium UK Ltd (Alcan) by issuing debt.  The Guarantee 

    did not directly support existing jobs.  As part of the agreement, Greensill Capital securitised the guarantee together 

    with forecasted revenue streams from the smelter to the supporting hydro- electric facility in order to provide loan-financing to GFG.  

    In the event that the guarantee was called in, it provided protection to Greensill (now in administration), not companies within GFG.

  •  While the Authority may claim that the Guarantee was offered on an even-handed basis to all prospective bidders, 

    it strongly favoured bidders using supply-chain finance as the mechanism of acquisition (such as GFG).  The offer provided 

    much less advantage, for example, to cash bidders and so the “even-handed” offer merely created an illusion of fairness.  

    The net effect of the guarantee offer to all bidders was to significantly elevate the attractiveness of the debt-financed 

    GFG bid.  (The Authority had an already-established relationship with GFG through its purchase of the Dalzell and Clydebridge steelworks.)

  • Alcan was not a distressed company at the time of acquisition by GFG and was trading profitably.  GFG purchased 

    the company for £330 million.  This was not the value of a distressed company.  The funding enabled by the Guarantee 

    was not “last resort funding” in relation to the Lochaber complex.

  • A stated objective of the Authority was to prevent the fragmentation of the Lochaber smelter complex.  However, 

    immediately after the acquisition, GFG removed the Lochaber smelter, Kinlochleven hydro-plant and estate land holdings 

    from the existing legal entity (Alcan), transferring them to new and separate legal entities under different structures ultimately controlled from different off-shore jurisdictions.

  • The Authority had represented that, in return for entering into the Guarantee, it received a “commercial fee”. There was no independent 

    evidence to support the assertion that the fee was at a commercial level.  If the arrangement was of a commercial level, 

    GFG could have obtained the Guarantee from the private sector where there are much lower transparency expectations.

  • High levels of secrecy over high-value government contracts were a red flag of potential fraud.  Fraudsters were extremely 

    unlikely to consent to disclosure of any information in any circumstance.  GFG is under investigation by the Serious Fraud Office for suspected fraud, 

    fraudulent trading and money-laundering including its financing arrangements with Greensill.  The Serious Fraud Office 

    has no jurisdiction in Scotland where there is no equivalent agency.

The Authority’s interests

33.    In addition to the background information above, the Authority explained that, as a result of its legal

obligations arising from the Guarantee, it had a significant and specific financial and economic interest in the

operation of the smelter to which the information related.  In addition, it had an overarching general interest in

the original objectives of the proposal, namely the retention of jobs and the support of the metals industry in

Scotland.

34.    The Authority acknowledged that the Commissioner had previously indicated in Decision 144/2021  that he

did not consider the Authority to be a commercial actor in respect of Scotland’s energy sector, but that it may

have other economic interests in relation to the smelter.

35.    The Authority considered that its commercial, economic and financial interests in respect of the Guarantee

were manifest and quantifiable, and information within the material remained current.  It also submitted that

there was considerable uncertainty with respect to any future scenario involving the smelter, the loss of which

could materially impact upon the local regional economy.  It noted that, during the 18 months since the Greensill

collapse, GFG and its primary shareholder, Sanjeev Gupta, had sought to defend and engage in legal action across

multiple jurisdictions in order to preserve operations.

Information falling within scope of the request

36.    Section 1(1) of FOISA provides that a person who requests information from a Scottish public authority

which holds it is entitled to be given that information by the authority, subject to qualifications which, by

virtue of section 1(6) of FOISA, allow Scottish public authorities to withhold information or charge a fee for it.  

The qualifications contained in section 1(6) are not applicable in this case.

37.    The information to be given is that held by the authority at the time the request is received, as defined

in section 1(4).

38.    The standard of proof to determine whether a Scottish public authority holds information is the civil

standard of the balance of probabilities.  In determining where the balance of probabilities lies, the

Commissioner considers the scope, quality, thoroughness and results of the searches carried out by the public

authority.  

39.    The Commissioner also considers, where appropriate, any reason offered by the public authority to explain

why it does not hold the information.  While it may be relevant as part of this exercise to explore expectations

about what the authority should hold, ultimately the Commissioner’s role is to determine what relevant recorded

information is (or was, at the time the request was received) actually held by the authority.

40.    The Authority identified and provided copies of two documents in redacted form considered to fall within

the scope of the request, consisting of seven and eight pages of email correspondence, respectively, dating

between 31 January 2020 and 18 May 2020.  

41.    During the investigation, the Commissioner asked the Authority how it had established what information it

held falling within the scope of the request, particularly because one email identified as falling within scope

referred to further correspondence which had not been provided.

42.    The Authority conducted further searches and, as rehearsed in paragraph 13, disclosed information that had

been published online in response to another request, which fell within scope of the Applicant’s request and

further information in an email dated 31 January 2020.

43.    The Authority also provided, as rehearsed in paragraph 14, an updated version of an email dated 9 March

2020.  The Authority withheld some of the additional information within the email under the exemption in section

30(c) of FOISA, together with the information that was previously withheld.

44.    Using the following keywords, the Authority carried out searches of its Electronic Record and Document and

Management System (eRDM), MiCase system  and the mailbox for the relevant business area:

  • “Greensill Capital”
  •  “Greensill”
  •  “Greensill Capital Guarantee & Reimbursement Agreement”
  • “Due diligence on Greensill Capital”

45.    In addition to this, the Authority carried out searches of the Strategic Industrial Projects team

mailboxes for emails from “@greensillcapital.co.uk”, “@greensillcapital.com” and “Lex Greensill”, as well as for

the keywords “Due diligence on Greensill Capital”.

46.    The Authority also instructed its legal and commercial advisers to carry out searches (on the same basis

as those it carried out on its own systems) for any relevant information held by them on its behalf.

47.    The Authority confirmed that it did not hold either the pricing supplements referred to in an email dated

9 March 2020 or the attachment in an email dated 18 April 2020, which were previously held on its behalf by its

legal advisers but had not been retained.

48.    Following these searches, the Authority confirmed that it held no further information falling within the

scope of the Applicant’s request.

The Commissioner’s view

49.    Having considered all relevant submissions and the terms the request, the Commissioner is satisfied that,

by the end of the investigation, the Authority had taken adequate, proportionate steps in the circumstances to

establish whether it held any information that fell within the scope of the request

50.    The Commissioner is satisfied that the searches carried out by the Authority were reasonable and

sufficient to determine whether the requested information was held.  The Commissioner is therefore satisfied, on

the balance of probabilities, that the Authority does not (and did not, on receipt of the request) hold any

information falling within the scope of the Applicant’s request

51.    However, as the Authority disclosed further information to the Applicant subsequent to its review

response, the Commissioner must find that the Authority failed to comply with section 1(1) of FOISA.


Section 30(c) – Prejudice to effective conduct of public affairs

52.    Section 30(c) of FOISA exempts information if its disclosure "would otherwise prejudice substantially, or

be likely to prejudice substantially, the effective conduct of public affairs".  This exemption is subject to the

public interest test in section 2(1)(b) of FOISA.

53.    The word "otherwise" distinguishes the harm required from that envisaged by the exemptions in sections

30(a) and (b).  This is a broad exemption and the Commissioner expects any public authority citing it to show what

specific harm would (or would be likely to) be caused to the conduct of public affairs by disclosure of the

information, and how that harm would be expected to follow from disclosure.

54.    The standard to be met in applying the tests contained in section 30(c) is high: the prejudice in question

must be substantial and therefore of real and demonstrable significance.  The Commissioner expects authorities to

demonstrate a real risk or likelihood of substantial prejudice at some time in the near (certainly foreseeable)

future, not simply that such prejudice is a remote or hypothetical possibility.  Each request should be considered

on a case by case basis, taking into consideration the content of the information and all other relevant

circumstances (which may include the timing of the request).

55.    The Authority relied upon section 30(c) (prejudice substantially, the effective conduct of public affairs)

to withhold information in the documents.  

The Authority’s submissions on section 30(c)

56.    The Authority submitted that it was essential for it to have a productive relationship with companies like

GFG, which run businesses of national and local importance to Scotland.  As the Lochaber smelter is a significant

employer in the local area, the Authority had a significant interest in the business through the Guarantee.

57.    The Authority provided three key reasons for withholding the information under the exemption in section

30(c) of FOISA, as follows:

Point (a) – Disclosure would weaken the Authority’s ability to negotiate guarantee terms

58.    The Authority submitted that it was likely that external lenders will be involved in situations where it

is providing guarantees to support businesses.  It would be in these lenders’ interests to negotiate the most

generous guarantee terms possible, thereby passing risk to the Authority (which would be to the detriment of the

Authority’s interests were such a guarantee more likely to be called up).  Disclosure would enable future lenders

to form views about the Authority’s likely appetite for risk and on how it takes decisions on these matters, and

would allow them to use this as part of their negotiation strategy.  The Authority believed the process of

benchmarking one guarantee against another would ultimately be detrimental to its interests.

Point (b) – Disclosure would make distressed businesses less likely to engage with Authority support

59.    The Authority submitted that businesses are extremely hesitant to consider financial intervention

sponsored by it, or its Agencies, due to the risk of this becoming public knowledge, as this would alert customers

and suppliers to the fact that the business was utilising last resort funding to continue to trade.  This, in

turn, would adversely affect the business as its customers and suppliers would be less willing to deal with it due

to fear of wasted costs (e.g. where the business was unable to pay for materials ordered), leading to further

difficulties in trading.

60.    In the Authority’s view, disclosure would exacerbate the issue by underscoring not only that fact, but

also the underlying basis on which decisions are made about sensitive business operations and situations, and this

risk was not one that arose where a business secured support from a third party which was not a Scottish public

authority.  The Authority also believed this would heighten concerns about seeking support from the Authority,

making such support less effective and thereby prejudicing its own commercial interests.

61.    The Authority argued that it must be able to assure businesses that sensitive information about their

financial position and future plans will not be released as a result of their involvement with the Authority.  In

the Authority’s view, maintenance of trust was important to allow it to engage with businesses in the best

interests of Scotland, with the ultimate aim of preserving employment and growing the economy.  It believed that

disclosure of the information would jeopardise its ability to work in partnership with commercial actors such as

GFG in future.

Point (c) – Disclosure would remove the private space for consideration that is required by the Authority to make

decisions in relation to a significant contract with implications for jobs and the economy

62.    The Authority submitted that the Guarantee was a live agreement, and it was required to take decisions in

relation to the management of the Guarantee.  It argued that release of information relating to the Guarantee,

including the terms of the Guarantee, would inhibit substantially its ability to make such decisions in the public

interest, by removing the private space required for it to do so.

63.    The Authority considered that disclosure would also substantially prejudice its relationship with GFG.  In

its view, disclosing the content of a live agreement to which GFG is party could negatively impact on GFG’s

financial operations in a number of stated ways.  The Authority believed that GFG would likely consider that it

had revealed sensitive details which were shared on a confidential basis in respect of the agreement, which would

be detrimental to GFG and its ongoing relationship with the Authority.

The Applicant’s submissions on section 30(c)

64.    The Applicant disagreed that the exemption in section 30(c) was engaged.  In their view, disclosure of the

withheld information would not result in the significant probability of substantial prejudice.

65.    In respect of point (a) above, the Applicant submitted that the Authority had not substantiated the link

between the specific information, disclosure and harm.  They argued that the Lochaber Smelter Guarantee and

Reimbursement Agreement (GRA) was a novel, highly unusual agreement with a financing firm (Greensill Capital (UK)

Ltd) which was not authorised and regulated by the Financial Conduct Authority, and which had subsequently

collapsed into administration.  In their view, the unique nature of this agreement would not compromise

negotiations in future guarantees.

66.    In respect of point (b) above, the Applicant did not believe there was any requirement for the Authority

to obtain the consent of the participating companies prior to disclosing information.  In their view, the

participating companies will have engaged into the GRA knowing that the Authority was a public authority for the

purposes of FOISA, and so information could be disclosed solely at the discretion of the Authority.  They argued

that the agreement should contain a clause to that effect.

The Commissioner’s view on section 30(c)

67.    Information can only be exempt under section 30(c) of FOISA if its disclosure would prejudice

substantially, or be likely to prejudice substantially, the effective conduct of public affairs.  

68.    The Commissioner must consider the withheld information with regard to the circumstances at the time of

the Authority’s review outcome.  Given the sensitivity of the information and the circumstances surrounding it,

the Commissioner is limited in the reasoning he can set out in this Decision Notice.

69.    The Commissioner notes that the main focus of the withheld information is financial arrangements and

discussions of the commercial companies’ information within the documents which were, at the date of the

Authority’s review response, relatively recent.

70.    For example, at the date of the Authority’s review response, the financial viability of the companies

involved (Greensill and CFG) had changed considerably, but the Authority would still have to pay for 80% of the

power that SmelterCo is contracted to purchase from HydroCo in the event that SmelterCo is unable to do so.

71.    Having considered the nature and content of the withheld information, together with the submissions of the

Authority and the Applicant, the Commissioner finds that disclosure of the withheld information would, or would be

likely to, have a detrimental impact on the Authority, CFG and the other commercial companies’ ability to continue

in a competitive environment, which, in turn, would, or would be likely to, impede the Authority’s ability to

engage with businesses in the best interests of Scotland.  

72.    The Commissioner cannot expand on his reasoning here, as to do so would reveal the information being

withheld.

73.    In the circumstances, the Commissioner is satisfied that the Authority was entitled to apply the exemption

in section 30(c) of FOISA to the withheld information.

Public interest test

74.    The exemption in section 30(c) is subject to the public interest test in section 2(1)(b) of FOISA.  The

Commissioner must therefore go on to consider whether, in all the circumstances of the case, the public interest

in disclosing the information is outweighed by that in maintaining the exemption.

The Authority's submissions on the public interest – section 30(c)

75.    The Authority recognised the public interest in disclosure, as part of an open, transparent and

accountable government and to inform public debate.  It also recognised the public interest in the aluminium

smelter complex, and in how the Authority works with companies such as GFG when public funds are involved.

76.    However, given the importance of the smelter to Scotland, the Authority believed this was outweighed by

the public interest in protecting GFG’s trust in its relationship with the Authority.

77.    The Authority argued that it was of vital importance to Scotland and its people that it was able to

intervene to protect jobs and the wider economy.  When this involved a guarantee, such as this one, the Authority

believed the public interest lay in protecting certain sensitive information to allow future interventions.

78.    The Authority submitted that, ultimately, the aim of this intervention was to protect jobs, and there was

no public interest in disclosing information that would jeopardise such future action.

79.    The Authority believed the public interest lay in protecting the interests of those employed within the

Lochaber smelter business (circa 200 people), given its importance not only to those employees, but also to the

wider economy of the local area.

The Applicant's submissions on the public interest – section 30(c)

80.    The Applicant submitted a number of arguments in support of their position that the public interest favoured disclosure of the information.  In their view, there was a public interest:

  • in ensuring the Guarantee agreement and the Authority’s actions complied with all laws and regulations;
  • in ensuring the Scottish Parliament’s Finance and Constitution Committee was provided with complete and accurate information by the Authority, and that it provided effective independent scrutiny prior to approving the £586m contingent liability;
  • in subjecting the financial guarantee to broad public scrutiny to increase the quality of the scrutiny

over that achievable by a small number of politicians (lay people);

  • in disclosure, because of suspected fraud and money-laundering between two of the key parties (GFG and

Greensill Capital (UK) Limited), because the Guarantee was not based on sound data, and because one of the key

parties to the agreement (Greensill Capital (UK) Limited) was now in administration;

  • in ensuring the agreement was robust and at arm’s length, with no mutual reward between the Authority and

other parties to the agreement, and that it provided value for money at all stages (from approval to delivery);

  • in disclosure, in order to evaluate relative spending priorities and to be able to independently monitor

and measure approved project outcomes;

  • in disclosure, because of the financial size (£586m), the unusual term (25 years), the nature and the complexity of the agreement;
  • in understanding the Authority’s exposure to the GRA; and
  • in understanding the security and guarantees the Authority has obtained from GFG member companies for entering into the agreement and, specifically, whether they were adequate.

81.    Separately, the Applicant made the following arguments (see paragraph 26) which were also relevant to the

public interest test:

  • the Guarantee did not directly support existing jobs;
  • the Guarantee provided protection to Greensill and not GFG;
  • the funding enabled by the Guarantee was not “last resort funding” in relation to the Lochaber complex;
  • the funding had not prevented the fragmentation of the Lochaber smelter complex;
  • there was no independent evidence to support the Authority’s assertion that the fee was at a commercial level; and
  • “secrecy” over high-value government contracts was a “red flag of potential fraud” and GFG was under

investigation by the Serious Fraud Office.

The Commissioner’s view on the public interest – section 30(c)

82.    The Commissioner has taken account of all of the relevant submissions from both parties, together with the

withheld information in this case.  He is required to balance the public interest in disclosure of the information

requested against the public interest in maintaining the exemption.  The public interest, in the context of FOISA,

should be considered as “something which is of serious concern and benefit to the public”.

83.    As rehearsed above, the Commissioner has already accepted that disclosure of the withheld information

would, or would be likely to, cause substantial prejudice to the effective conduct of public affairs.

84.    Given the significant size of the Lochaber Smelter Guarantee and those potentially affected by the

circumstances surrounding it, the Commissioner accepts that there is clear and substantial public interest in

understanding the finer details of the Guarantee and discussions that the Authority had with Greensill and other

companies.

85.    However, the Commissioner recognises that this must be carefully balanced against any impact that

disclosure of the withheld information would have had – at the time when the Authority issued its review outcome –

with regard to the Lochaber smelter, the Guarantee itself (underwritten by the Authority) and what the likely

circumstances might be were the Guarantee to be called in.

86.    The Commissioner acknowledges that, were circumstances to arise requiring the Guarantee to be called in,

this would clearly impact the parties involved (including the Authority), the economy of the local area (and the

wider Scottish economy) and the jobs of those individuals employed at the smelter and associated businesses, both

directly and indirectly.

87.    The Commissioner recognises that such a situation could lead to a number of unwanted circumstances

presenting themselves, for example job losses, the requirement for a new agreement to be drawn up or entered into

by the Authority, and a reduction in crucial commercial information being provided by businesses to the Authority

which would inhibit the Authority’s ability to take fully informed decisions and secure best value for public

money.  Such circumstances would clearly impact on the Authority’s position with regard to its ability to

effectively conduct its public affairs, and that would not be in the public interest.

88.    On balance, therefore, the Commissioner is of the view that the public interest in withholding the

remaining information outweighs the public interest in disclosing it.

89.    The Commissioner therefore finds that the Authority was entitled to withhold the information he has found

to be exempt under section 30(c) of FOISA.


Decision

The Commissioner finds that the Authority partially complied with Part 1 of the Freedom of Information (Scotland)

Act 2002 (FOISA) in responding to the information request made by the Applicant.  


The Commissioner finds that, by relying upon section 30(c) of FOISA to withhold information within the documents,

the Authority complied with Part 1.


However, by disclosing further information to the Applicant subsequent to its review response, the Authority

failed to comply with section 1(1) of FOISA.


Given that all non-exempt information has been disclosed, the Commissioner does not require the Authority to take

any action in respect of this failure in response to the Applicant’s application.


Appeal


Should either the Applicant or the Authority wish to appeal against this decision, they have the right to appeal

to the Court of Session on a point of law only. Any such appeal must be made within 42 days after the date of

intimation of this decision.


David Hamilton
Scottish Information Commissioner

4 June 2024

Appendix 1: Relevant statutory provisions

Freedom of Information (Scotland) Act 2002

1     General entitlement


(1)     A person who requests information from a Scottish public authority which holds it is entitled to be given

it by the authority.

(2)     The person who makes such a request is in this Part and in Parts 2 and 7 referred to as the “applicant.”

(4)    The information to be given by the authority is that held by it at the time the request is received,

except that, subject to subsection (5), any amendment or deletion which would have been made, regardless of the

receipt of the request, between that time and the time it gives the information may be made before the information

is given.

(6)    This section is subject to sections 2, 9, 12 and 14.


2     Effect of exemptions

(1)     To information which is exempt information by virtue of any provision of Part 2, section 1 applies only to

the extent that –

(a)    the provision does not confer absolute exemption; and

(b)     in all the circumstances of the case, the public interest in disclosing the information is not outweighed

by that in maintaining the exemption.
….


30     Prejudice to effective conduct of public affairs

Information is exempt information if its disclosure under this Act-

(c)     would otherwise prejudice substantially, or be likely to prejudice     substantially, the effective

conduct of public affairs.

47     Application for decision by Commissioner

(1)     A person who is dissatisfied with -

(a)     a notice under section 21(5) or (9); or

(b)     the failure of a Scottish public authority to which a requirement for review was made to give such a

notice.

may make application to the Commissioner for a decision whether, in any respect specified in that application, the

request for information to which the requirement relates has been dealt with in accordance with Part 1 of this

Act.

(2)     An application under subsection (1) must -

(a)     be in writing or in another form which, by reason of its having some permanency, is capable of being used 
for subsequent reference (as, for example, a recording made on audio or video tape);

(b)     state the name of the applicant and an address for correspondence; and

(c)     specify –

    (i)    the request for information to which the requirement for review relates;

    (ii)    the matter which was specified under sub-paragraph (ii) of section 20(3)(c); and

    (iii)    the matter which gives rise to the dissatisfaction mentioned in subsection (1).